       on the morning of june 15, inner mongolia zhongyuan dingyuan fertilizer co., ltd. potash calcium magnesium magnesium fertilizer production line project according to plan to achieve 6.15 stand-alone test. the contract for the installation of mechanical and electrical equipment was signed in 2016 october, during which the winter break 3 months. our company undertakes all the mechanical and electrical equipment, raw material system, raw meal system, firing system, cooling system, grinding system, packaging system and so on all the mechanical and electrical equipment, non-standard installation and kiln preheater and tower steel structure installation and installation tasks.

 
by jin hailong